Wednesday, April 15, 2009

DECEMBER

MONTH FOUR

2nd December window frames skirts archs and doors underway

more architrave and a little bit of skirting board

window frame

its all coming together now

window frame


19th December- painter done for round one and bench top is in (quantum quartz- Ice)
Paint is new soft blush for walls and chalkdust on archs skirts and window frames and doors

kitchen

benchtop is on....16th December

painting in the bedroom


painting is done on walls, roof, window frames.....just skirts to go

painting in bedroom



24th December rendering has been started (now its time for the Christmas break)

rendering is underway




At this point our SS was predicting a late February early march handover date